Pregunta:
What happened AFTER the Flood in terms of Management Strategies?
Autor: eric_galvaoRespuesta:
-Government made the 'Somerset Levels and Moors Flood Action Plan' which is a Plan lasting 20 Years that deals with Future Flooding. Around £100 Million will be spent on: 1. Temporary Pumping Station --> Permanent Pumping Stations 2. Regular dredging the River Parett, and the River Tone 3. Constructing a Tidal Barrage at Bridgewater 4. Widening the River Sowy's Channel, and the King's Sedgemoor Drain.