Por supuesto:
(Practica preguntas similares gratis)
Chapter 1 - A new approach for complex problems
» Iniciar este curso(Practica preguntas similares gratis)
Pregunta:
In the Sprint Review, the presentation of the product Increment to stakeholders is a) To get the Sprint completion sign-off. b) To provide the status of the project. c) To elicit feedback.
Autor: Avinash UpadhyayRespuesta:
C) To elicit feedback. The Sprint Review is an informal meeting, not a status meeting, and the presentation of the Increment is intended to elicit feedback and foster collaboration. Correct answer is ‘c.’
0 / 5 (0 calificaciones)
1 answer(s) in total