Pregunta:

The increment is a step towards a) A vision or goal. b) Sprint completion or project closure. c) Sign-off or phase completion.

Autor: Avinash Upadhyay



Respuesta:

A) A vision or goal. The Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints. An increment is a body of inspectable, done work that supports empiricism at the end of the Sprint. The increment is a step toward a vision or goal. Correct answer is ‘a.’