Pregunta:
A situation when a contractor performs work beyond the contract requirements, without a formal order under the changes clause, either due to an informal order from, or through the fault of, the buyer
Autor: Ratna LikhitaRespuesta:
Constructive change
0 / 5 (0 calificaciones)
1 answer(s) in total