Pregunta:
How would you typically calculate the production budget?
Autor: Hjalmer PedersenRespuesta:
Budgeted sales + target closing finished goods stock - opening finished goods stock = Units to be produced
0 / 5 (0 calificaciones)

1 answer(s) in total