Pregunta:
Which are true statements? select all that apply. a) The Scrum team is responsible for formulating the sprint goal. b) When existing product backlog items in the Sprint backlog are modified, the sprint goal is bound to become invalid. c) The coherence between product backlog items is made transparent by the sprint Goal. Lack of Coherence will lead to the developers working individually
Autor: Avinash UpadhyayRespuesta:
A) The Scrum team is responsible for formulating the sprint goal. c) The coherence between product backlog items is made transparent by the sprint Goal. Lack of Coherence will lead to the developers working individually