Pregunta:

In sprint review, along with the review of the product increment and progress, "What (Steps) to do next" is also discussed. a) False b) True the scope of next increment is also finalized here. c) True, it may capture probable backlog items for the next sprint, but the scope of the next sprint is deferred until sprint planning.

Autor: Avinash Upadhyay



Respuesta:

C) True, it may capture probable backlog items for the next sprint, but the scope of the next sprint is deferred until sprint planning.