Pregunta:
After the Sprint Review, Production release in Scrum requires a) Hardening Sprint b) Non Functional Testing c)Architectural Validations d)Usability and end user testing e) All of the above f)None of the above
Autor: Avinash UpadhyayRespuesta:
F)None of the above Every sprint must produce an increment that is valuable and useful. This means that the increment is potentially releasable to production with minimal work.