Pregunta:
In which event are the cost and the number of sprints decided?
Autor: Avinash UpadhyayRespuesta:
Parameters like release date, cost etc are reviewed in the Sprint Review. However Scrum leaves it open about their definition. Unless otherwise inferred through the question, it is safe to assume that they are defined at the time when the just enough backlog is defined before the first sprint.