Pregunta:

In a retrospective, a scrum Team decides to revise the Sprint length. The New Sprint Length needs to be agreed upon by the Product owner a) True b) False

Autor: Avinash Upadhyay



Respuesta:

A) True The Product owner needs to ensure that the Sprint Length is short enough to limit business risks and also short enough so the team can synchronize the Development work with other Business events . So it requires the Approval of the Product owner. Please note that the finalized Sprint length cannot be longer than 1 calendar month . Correct answer is "a"