All activities that happen within Scrum are called Scrum Events a) True b) False

Autor: Avinash Upadhyay



Respuesta:

There can be any number of activities within the Scrum framework as chosen by the Scrum team. It will include Development work practices, Backlog Refinement etc. However all the activities are not scrum events. There are only five defined events in Scrum. Correct answer is "b"