Pregunta:
In the first few Sprints, the Developers are expected to focus on a) Setting up the basic infrastructure needed for subsequent Sprint work. b) Reviewing and baselining the project plan so the changes can be controlled. c) Iteratively refining the requirements and obtaining sign-off from the Product Owner. d) Delivering a valuable and useful product Increment. e) All of the above.
Autor: Avinash UpadhyayRespuesta:
D) Delivering a valuable and useful product Increment. The Developers must try to deliver at least one piece of functionality NOT only in the first few Sprints but in every single Sprint. Correct answer is ‘d.’