A Developer identifies a technical issue that requires other Developers to work together to solve this. Who needs to facilitate this? a) Product Owner b) Scrum Master c) Developers
Autor: Avinash UpadhyayRespuesta:
C) Developers The Developers are responsible for performing development work and meeting the Sprint Goal. If they have any issue that is within their influence to solve, they are responsible for resolving it. The Scrum Master is responsible for impediments that are outside the Scrum Team's influence. Correct answer is ‘c.’