Pregunta:
What is used by the Scrum Team to identify unfinished work in a Sprint? a) Coding Standard b) Definition of Ready c) Testing Standard d) Definition of Done
Autor: Avinash UpadhyayRespuesta:
D) Definition of Done The Definition of Done provides the same shared understanding of what it means for the work to be complete. It spells out all that is required to get the work ‘done.’ So, it is used by the team to assess what is yet to be done to complete the product Increment. Everybody developing the same shared understanding is the key to transparency. Correct answer is ‘d.’