Pregunta:

An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time- consuming and most reliable methods to predict project costs.

Autor: Mitch Palmer



Respuesta:

Bottom-up estimating